| Sabz Ab/Tang Fanni/Shazand/Rey Sour crude pipeline project | 33.927495 | 49.41277 | Sabzab/Tang Fanni pipelines with estimated 100 kms of 30 inches pipe size with the capacity to transfer 450,000 bpd crude | Pipelines and Related Facilities Projects | No | Logo | /en/Pages/Plans and Projects/Ongoing Projects/PipelinesandRelatedFacilitiesProjects/Installation-of-Abadan-Ray-pipeline_Sabzab-Ray-pipe-line-.aspx | [{'k':33.090530,'B':47.722700},{'k':33.927495,'B':49.412770},{'k':35.575030,'B':51.444995}] | 7a1225 |
| Naeen-Kashan-Rey Pipeline | 32.698657 | 51.577407 | The project includes 420 kms 20 inch pipelines, 420 kms optic fiber cables, setting up 10 swing storage tanks for products in Naeen, installations of a crude pumping station in Naeen and Kashan, a terminal in Rey, two 63 kilovolt power stations in Naeen a | Pipelines and Related Facilities Projects | No | Logo | /en/Pages/Plans and Projects/Ongoing Projects/PipelinesandRelatedFacilitiesProjects/Installation-of-Naein-Kashan-Ray.aspx | [{'k':32.859977,'B':53.087397},{'k':32.698657,'B':51.577407},{'k':35.575030,'B':51.444995}] | E330D4 |
| Laying complementary 26 inch Back Area pipelines/Mahshahr exporting port | 30.4557767693749 | 49.1761779785156 | Laying the addition of 26 inch pipeline from Back Area oil storage facilities to the exporting port to facilitate exports | Pipelines and Related Facilities Projects | No | Logo | /en/Pages/Plans and Projects/Ongoing Projects/PipelinesandRelatedFacilitiesProjects/Installation-of-26-complementary-pipeline-,-Back-Area-–-mahshahr-Exporting-port.aspx | [{'k':30.335267,'B':49.298753},{'k':30.581492,'B':49.046068}] | 306C80 |
| Updating Mahshahr Exporting Port (Including establishment of sulfur jetty) | 30.2774117292983 | 49.515380859375 | Updating and reconstruction of old equipment inMahshahr exporting port to raise the productivity potential to meet growing needs for exports and imports of oil products in the coming years. | Jetty Projects | No | Logo | /en/Pages/Plans and Projects/Ongoing Projects/JettyProjects/Mahshahr-ExpMahshahr-Exporting-Port-Rehabilitationorting-Port-Rehabilitation.aspx | | |
| Pipelines to transfer fuel to Chabahar power plant | 25.4624531101167 | 60.919189453125 | • Construction of about 20 kms pipeline • Commissioning pumping station in eastern side of Chabahar oil storage • Commissioning a terminal on eastern side of Chabahar power plant storage tank • Piping path improvement | Pipelines and Related Facilities Projects | No | /MapsImages/_w/khateloole_JPG.jpg | /en/Pages/Plans and Projects/Ongoing Projects/PipelinesandRelatedFacilitiesProjects/Installation-of-14--fuel-supply-pipeline-of-Chabahar-power-station.aspx | [{'k':25.278347,'B':60.669667}] | D5ACE3 |
| Construction of pumping stations and terminals in Abadan-Mahshahr | 30.4699813962213 | 48.7820434570313 | Renovation, improvement and updating of the facilitiesthat transfer and receive crude oil, crude resid and other crude products from Abadan refinery, pumping stations in 40 miles away from Mahshahr, and new management facilities (including 7 pumping stati | Pipelines and Related Facilities Projects | No | /MapsImages/_w/khateloole_JPG.jpg | /en/Pages/Plans and Projects/Ongoing Projects/PipelinesandRelatedFacilitiesProjects/Installation-ofthe-new-pump-stationstations-and-oil-terminals-of-Abadan-and-Mahshahr.aspx | [{'k':30.349974,'B':48.296229},{'k':30.558823,'B':49.198183}] | ED3C28 |
| Abadan-Ahvaz-Arak-Tehran Pipeline | 31.31621 | 48.670592 | • Construction of 650 km pipeline including: o Abadan-Ahvaz pipeline -140 kms, 26 inches pipe size o Ahvaz-Sabzab pipeline - 120 kms, 24 inches pipe size o Sabzab-Tang Fani pipeline -100 kms, 24 inches pipe size o Shazand-Arak-Rey pipeline -290 kms, 26 in | Pipelines and Related Facilities Projects | No | /MapsImages/_w/khateloole_JPG.jpg | /en/Pages/Plans and Projects/Ongoing Projects/PipelinesandRelatedFacilitiesProjects/Installation-ofAbadan-Arak-Ray-product-pipeline.aspx | [{'k':30.345826,'B':48.294856},{'k':31.316210,'B':48.670592},{'k':34.090357,'B':49.689853},{'k':35.691516,'B':51.423976}] | 22946E |
| Pipelines and facilities constructionto transfer of refinery productsbetween Tabriz-Khoy-Orumieh | 38.549303 | 44.952836 | Construction of 14 inch pipelines size from Tabriz to Orumiehwith 10 inch pipe size branch toKhoy, commissioning of Tabriz and Salman pumping stations, with Khoyand Orumieh terminals. | Pipelines and Related Facilities Projects | No | /MapsImages/_w/khateloole_JPG.jpg | /en/Pages/Plans and Projects/Ongoing Projects/PipelinesandRelatedFacilitiesProjects/Installation-offacilitiesTabriz-Khoy-Oroumieh-oil-product-pipeline-and-related-facilities.aspx | [{'k':38.060097,'B':46.297159},{'k':38.549303,'B':44.952836},{'k':37.556114,'B':45.071776}] | 7A3925 |
| Increase and establish Abadan Refinery capacity | 30.3727171794256 | 48.6776733398438 | Abadan refinery currently operateswith 400,000 bpd crude capacity, of which 250,000 bpd is processedin three crude distillation units with the record serviceexceeding 70 years. Consideringits oldtechnology and equipment, the three crude distillation units | Refinery Projects | No | /MapsImages/_w/palayeshgah_jpg.jpg | /en/Pages/Plans and Projects/Ongoing Projects/RefinaryProjects/development-and-capacity-stabilization-of-Abadan-refinery–Phase-2.aspx | | |
| Capacity increase and quality improvement of Imam Khomeini Refinery in Shazand of Arak, Iran | 34.0845119344748 | 49.7062683105469 | In the direction of the reform initiative to change the country’sconsumptionof crude fractionation mid-distillate products to gasoline, and to upgrade quality of the products inArak Refinery based oninternational standards, Imam Khomeini Refinery developm | Refinery Projects | No | /MapsImages/_w/palayeshgah_jpg.jpg | /en/Pages/Plans and Projects/Ongoing Projects/RefinaryProjects/Imam-Khomeini-Shazand-Refinery-Expansion-and-Upgrading-Project.aspx | | |
| Optimization of Isfahan Refinery project,North Section(DRP) | 33.0270875800287 | 52.1630859375 | Construction of distillation unit No. 3, gas liquification No.3, and kerosene refining units. | Refinery Projects | No | /MapsImages/_w/palayeshgah_jpg.jpg | /en/Pages/Plans and Projects/Ongoing Projects/RefinaryProjects/Optimization-Northern--side-of-Esfahan-Refinery.aspx | | |
| Completion and development of oil products export/import facilities in BandarAbbas | 27.1360644865447 | 57.32666015625 | Commissioning of four meter ultrasonic 16 instrument and 5 meter ultrasonic 12 instruments and installation and operation of two prover 24 crude resid and blended products systems | Jetty Projects | No | /MapsImages/eskele.jpg | /en/Pages/Plans and Projects/Ongoing Projects/JettyProjects/Installation-of-Bandar-abbas-new-Storage-tanks.aspx | | |
| Pipelines construction to transfer refinery products between Rey-Kan and Rey-Ghouchak | 35.699323 | 51.418483 | Pipelines construction around Tehran from Rey storage to Kanstorage facilities in northwest of Tehran and Ghouchakstorage facilities in northeast of greater Tehran | Pipelines and Related Facilities Projects | No | /MapsImages/_w/khateloole_JPG.jpg | /en/Pages/Plans and Projects/Ongoing Projects/PipelinesandRelatedFacilitiesProjects/Tehran-Bypass-Piplines-Project.aspx | | |
| Laying New Bandar Abbas-Sirjan-Rafsanjan Pipeline | 29.460188 | 55.670627 | • 468 kms 26 inch pipelines from Bandar Abbas pumping station to Rafsanjan terminal | Pipelines and Related Facilities Projects | No | /MapsImages/_w/khateloole_JPG.jpg | /en/Pages/Plans and Projects/Ongoing Projects/PipelinesandRelatedFacilitiesProjects/Installation-of-Bandarabbas--Sirjan-Rafsanjan-26--pipeline.aspx | [{'k':27.176339,'B':56.265364},{'k':29.460188,'B':55.670627},{'k':30.407484,'B':55.993195}] | 187326 |
| Goureh-Jask Crude Oil Pipeline Construction | 25.653385 | 57.782127 | Planned construction of a 1,100-kilometer pipeline, 42-inch diameter, for transferring 1 mb/d of crude oil from Goureh oil terminal in the northwest of Bushehr Province to the west of Jask region off the Sea of Oman | Pipelines and Related Facilities Projects | No | http://www.nioec.com/MapsImages/_w/khateloole_JPG.jpg | /en/Pages/Plans and Projects/Ongoing Projects/PipelinesandRelatedFacilitiesProjects/Goreh-Jask.aspx | | |
| Oil Installations Construction at Jask Port | 25.653385 | 57.782127 | Construction of crude oil storage tanks, accessories and offshore installations in Jask region in Hormuzgan Province on the build-operate-transfer (BOT) basis will be awarded to competent private entity. Investor is required to handle designing, engineeri | Jetty Projects | No | http://www.nioec.com/MapsImages/_w/eskele_jpg.jpg | /en/Pages/Plans and Projects/Ongoing Projects/JettyProjects/Jask.aspx | | |
| Process optimization and products quality improvement in ShahidTondguyan Refinery, Tehran, Iran. | 35.649577 | 51.398533 | To reducesulfurcontents inkerosene and gasoil products per Euro 5 standard,commissioningof newand debottlenecking of existingunits were put on the agendaforTehran’s ShahidTondguyan Refinery. | Refinery Projects | No | /MapsImages/_w/palayeshgah_jpg.jpg | /en/Pages/Plans%20and%20Projects/Ongoing%20Projects/RefinaryProjects/ShahidTondguyanRefinery.aspx | | |
| Pipeline constructionto transfer Farashband Gas plantdistillates to Shiraz Refinery | 28.854288 | 52.098455 | Construction of 231 km 8 inch pipeline from Dalan gas plant to Shiraz oil refinery | Pipelines and Related Facilities Projects | No | http://www.nioec.com/MapsImages/_w/khateloole_JPG.jpg | /en/Pages/Plans and Projects/Ongoing Projects/PipelinesandRelatedFacilitiesProjects/Pipeline-constructionto-transfer-Farashband-Gas.aspx | [{'k':28.854288,'B':52.098455},{'k':29.596267,'B':52.581709}] | 7a1225 |
| Completion of BandarAbbas-Isfahan products transfer capacity increase project | 27.182114 | 56.276338 | Construction of 231 km 8 inch pipeline from Dalan gas plant to Shiraz oil refinery | Pipelines and Related Facilities Projects | No | http://www.nioec.com/MapsImages/_w/khateloole_JPG.jpg | /en/Pages/Plans and Projects/Ongoing Projects/PipelinesandRelatedFacilitiesProjects/Completion-of-BandarAbbas-Isfahan-products.aspx | | |
| Construction of crude swingstorage tanks in Sari and Moghanak | 36.564876 | 53.059574 | Construction of four swing storage tanks and 4 water storage tanks for firefighting in Sari and Moghanak on Neka-Rey pipeline path | Pipelines and Related Facilities Projects | No | http://www.nioec.com/MapsImages/_w/khateloole_JPG.jpg | /en/Pages/Plans and Projects/Ongoing Projects/PipelinesandRelatedFacilitiesProjects/Construction-of-crude-swingstorage-tanks-in-Sari-and-Moghanak.aspx | | |
| Construction of water pipeline from BahmanshirRiver to Abadan refinery | 30.347085 | 48.299307 | Construction of about 7 kilometers of 8 inch pipelines between BahmanshirRiver and Abadan refinery along with two pumping stations and side equipment including power stations, control room and water basin reconstruction | Pipelines and Related Facilities Projects | No | http://www.nioec.com/MapsImages/_w/khateloole_JPG.jpg | /en/Pages/Plans and Projects/Ongoing Projects/PipelinesandRelatedFacilitiesProjects/Construction-of-water-pipeline-from-BahmanshirRiver-to-Abadan-refinery.aspx | | |
| Tehran side-way pipelines (Civil Defense Project) | 35.695618 | 51.39856 | Pipelines including 127 kms of 20 inches pipeline from Cheshme Shour to Eshtehard, 107 kmsof 24 inches pipeline from Cheshme Shour to Eyvanaki, 90 kms of 26 inches pipeline from Cheshme Shour to Palangabadwith branches of existing pipelines to inside the | Pipelines and Related Facilities Projects | No | http://www.nioec.com/MapsImages/_w/khateloole_JPG.jpg | /en/Pages/Plans and Projects/Ongoing Projects/PipelinesandRelatedFacilitiesProjects/Tehran-side-way-pipelines.aspx | | |
| Storage tanks in Jamal Ahmad District of Bandar Abbas | 27.981194 | 52.145973 | Basic design and implementation of the project in EPC model | Pipelines and Related Facilities Projects | No | http://www.nioec.com/MapsImages/_w/khateloole_JPG.jpg | /en/Pages/Plans and Projects/Ongoing Projects/PipelinesandRelatedFacilitiesProjects/Storage-tanks-in-Jamal-Ahmad-District-of-BandarAbbas.aspx | | |